Latest Construction Completion Dates

Construction

Since November 8, a great deal of planning has occurred to ensure the students of the Smithville School District have a premier learning environment no later than the fall of 2018.  The construction schedule has been updated accordingly, most notable since the first communication, the renovation work at Smithville Primary Elementary School has been pushed back to the summer of 2018 due to access to mechanical systems and construction materials without exceeding the forecasted project budget based on our schedule.  

 

 
Question 1

General obligation bond resulting in approximately 12.5 million in improvements

 

Current Smithville Primary Elementary School

Reconfigure main entrance, lobby, and nurse’s area – fall 2018

Bus and parking improvements – fall 2018

Classroom remodel, HVAC upgrades, acoustical – fall 2018

Roofing improvements – fall 2018

 

Current Smithville Upper Elementary School

Maker’s space and acoustical improvements – fall 2018

 

Smithville Middle School

Band room renovation – fall 2017

SILC modifications – fall 2017

 

Smithville High School

Cafeteria addition – fall 2018

Two-story addition – fall 2018

https://ssl.gstatic.com/ui/v1/icons/mail/images/cleardot.gifRoofing improvements – fall 2017

Asphalt improvement – fall 2017

Track resurface – fall 2017

Science lab remodel, counselors space improvements – fall 2018

 

Question 2

Approximately 21 million in improvements

 

Additional Elementary

PK-6 elementary – fall 2018

 

Revised:  December 13, 2016

 